Bloomberg reported that two Chinese companies installed Nvidia Blackwell-class hardware at a Shanghai facility called the Yangtze River Delta Project, based on loan documents it reviewed. Shanghai Shuoyao pledged a GB300 NVL72 rack as collateral for a 96 million yuan loan, roughly $14 million, from Shanghai Innovation Bank. A second company, Shanghai Kezhan, listed a GB200 server and 32 H200 servers at the same site. Shuoyao has acknowledged that it is a service provider to Megaspeed, which it describes as ordinary commercial cooperation. The Next Web carried a summary of the Bloomberg findings.
Megaspeed was founded in 2023 by Alice Huang, who left the company in August 2025 according to The Brief's account of Bloomberg's reporting. In 2024, Megaspeed used a rendering of the same site in an investor presentation without naming China as the location. Bloomberg reported that Kezhan is 83.3% owned by NeXPower Japan, a company Caixin has reported is controlled by Huang. Bloomberg said it had no evidence that Megaspeed itself sent the equipment to the site, and Megaspeed denies wrongdoing in the US probe. Nvidia and Megaspeed did not respond to Bloomberg's questions about the project.
The US Commerce Department added Megaspeed and six affiliates to its Entity List on November 23, according to Fox Business and BigGo Finance. The affiliates are based in Malaysia, Singapore and Thailand. Nvidia had already placed Megaspeed on its own no-sell list in June 2025, and the Justice Department is running a criminal investigation.
Why it matters
For companies that rent GPU capacity, export exposure follows the physical location and the operator of the hardware, not only the vendor that sold it. A lease, reseller contract or managed-service agreement can pull a buyer into a restricted chain even if the buyer never handled the chips. Lenders also take hardware as collateral, so a rack pledged to a bank can become a traceable asset tied to a listed party.
Founders, operators and investors should treat counterparty diligence as a gating item before signing. Request end-user documentation, the ownership chain of any data center, and the exact site address, then confirm capacity is where the contract says it is. Investors should check whether portfolio companies buy through partners that sit on the Entity List or on a supplier's no-sell list, because a listing can strand contracts and capacity quickly.
Key points
- 1Loan filings show a GB300 NVL72 rack pledged as collateral for a 96 million yuan loan.
- 2Shanghai Kezhan listed a GB200 server and 32 H200 servers at the Yangtze River Delta Project.
- 3Commerce added Megaspeed and six affiliates to the Entity List, its first addition since October 2025.
- 4Nvidia placed Megaspeed on its no-sell list in June 2025, and the Justice Department runs a criminal probe.
- 5Bloomberg found no evidence Megaspeed itself moved the hardware, and Megaspeed denies wrongdoing.